While the Ohio Department of Transportation (ODOT) wraps up most of its construction projects for the year, resurfacing efforts remain active in Crawford and Richland Counties. Both projects aim to improve roadway surfaces and safety, with ongoing lane closures and work scheduled through the end of 2024.
Crawford County: U.S. 30 Resurfacing Underway
ODOT has initiated resurfacing along U.S. Route 30 in Crawford County. The stretch from State Route 98 to just east of State Route 602 will experience single-lane closures to facilitate resurfacing and minor bridge work.
- Work Area: U.S. 30 from SR 98 to just east of SR 602
- Traffic Impact: Single-lane closures in both directions; traffic maintained throughout
- Additional Work: Minor bridge work included
- Estimated Completion: December 2024
ODOT assures drivers that traffic will be maintained at all times, minimizing delays for commuters and local travelers.
Richland County: State Route 13 Resurfacing Continues
The resurfacing of State Route 13 in Richland County has been marked by long-term, daily, and nightly single-lane closures. The project extends from Hanley Road to Chilton Avenue, with traffic maintained through 11-foot lanes, barrels, and temporary striping.
- Work Area: SR 13 from Hanley Road to Chilton Avenue
- Traffic Management: Long-term single-lane closures, 11-foot lanes, work zone striping
- Current Status: Inside passing lanes are closed northbound and southbound from just north of the I-71 ramp to Chilton Ave; crews are replacing median shoulder asphalt to prep for next season
- Estimated Completion for 2024: November 2024
- Full Project Completion: May 2027
Despite these restrictions, ODOT is maintaining traffic flow throughout the work zone.
Continuing Impacts for SR 13 Project
Currently, northbound and southbound inside passing lanes are closed from just north of the I-71 ramp to Chilton Avenue. This closure is necessary to replace the median shoulder asphalt, an essential step in preparing for next season’s construction phase. Preliminary project work is progressing steadily, ensuring timely completion of the resurfacing efforts slated for 2024.
Key Takeaways for Commuters
- Lane Closures: Single-lane restrictions are active in both counties, with traffic flow maintained.
- Safety Precautions: Drivers should be cautious and watch for barrels, lane changes, and work zone striping.
- Completion Dates: While major resurfacing efforts aim to finish by the end of this year, some work will continue into 2027.
Drive safely, stay alert in work zones, and plan for potential delays!